(Archived document, may contain errors)
Congressional Misperceptions and the SDI Battle of the Budget
By Ambassador Henry F. Cooper I welcome the opportunity to talk
with you at this critical time in our program, in view of the
upcoming continuation of the debate in the Congress, and in the
Senate in particular, on the President's FY1993 budget request for
the SDI program. This is a continuation of the many con- tentious
debates inmveral quarters -regardi n g SDI throughout its history.
. Generally I have categorized our efforts to advance the SDI
objectives in terms of three catego- ries of negotiations: 1) with
Congress, 2) within the Pentagon, and 3) with the Soviets, and now
the Russians. It is hard to k e ep the progress in these three key
areas uniform. It seems rather nor- mal that we take two steps
forward and one step back-and this is a very complicated process to
manage since the three areas of activity are coupled, and yet they
are, not being conduct ed in any sort of a synchronous fashion.
Congressional Backsliding Witness the performance of the Congress
over the past year. Last year, the Missile Defense Act of 1991 was
an enormously important step forward, and now the congressional
debate is over how far to regress from that very positive step. The
Bumpers-Sasser Amendment, which is the principal issue to be taken
up if the Senate does move the Defense Authorization Bill back on
the floor, is potentially lethal to our program. If it becomes law,
it w o uld scuttle any meaningful defense for the United States.
You should understand that the Bumpers-Sasser amendment is not only
premised on a $3.3 bil- lion budget this year-a cut of $2.1 billion
from the President's FY 1993 budget request, but it is derive d
from a flawed plan put forward by the Congressional Budget Office
(CBO) which would essentially cut the President's planned budget in
half for the out years. In my judgment, that plan would leave us
with no executable program for defending the United Sta t es
against ballistic mis- sile attack. We would have a viable program
for theater defense, but everything else would be research only.
There is some argument, I would suspect, as to whether the
CBO-proposed level of funding for the non-theater defense pro g ram
is sustainable-it is clearly sub-critical for a seri- ous
development activity, and it may not be sustainable as a research
activity during the current time of severe budget pressures. During
the Senate debate in August, some Senators (particularly Se n ators
Sasser and Levin) al- leged that with these reduced funding levels
one could proceed with a program aimed at deployment in the 2002
time frame. In fact, as I will discuss in some detail in a moment,
that is just simply not the case. If this major cu t were approved,
it would be particularly disappointing given the progress that we
have made over the past year in the other two problem areas; i.e.,
in negotiating our way through the Pentagon acquisition process and
in our discussions with the former Sov iet Union, notably with
Russia. Let me review our progress in those areas and then discuss
in more detail
Ambassador Cooper is Director of the Strategic Defense
Initiative Organization. He spoke at The Heritage Foundation on
September 8, 1992. ISSN 0272-1155. 01992 by The Heritage
Foundation.
the flawed Congressional Budget Office analysis and assumptions,
which I think are a major cause of misperception on Capitol Hill.
Progress In the Pentagon Probably the most important thing that has
happened in the Pentagon's battle over SDI since the advent of the
program was the 180-day Report to Congress describing the
Secretary's plan for implementing the Missile Defense Act of 1 9
91. 1 want to emphasize that this plan, signed out by Secretary
Cheney on July 2, was coordinated from the bottom up through the
various staffs of the Pentagon. It was fully coordinated with all
of the key acquisition officials, who signed on to that repo r t.
There were disagreements along the way. But at the end of the day,
we had a Depart- ment report and not just simply the Secretary's
report mandated from the top to be executed somehow later. So, now
we have a serious acquisition plan. It is an event - d riven
plan-and through the dem- onstration/validation phase over the next
five years, we have thought through the specifics of the program to
identify and schedule specific key events, in many cases test
events, where successful performance is necessary t o take the next
programmatic step. If Congress doesn't provide the money to do the
testing or to go through these events, obviously the program will
be delayed. Let me say just a word or two about our baseline
acquisition plan, which I think is misunder- s t ood. Assuming that
the President's budget request is honored-and that is an important
premise, our acquisition plan begins with five years of a highly
intensive demonstration and vali- dation (Dem/Val) testing program
with heavy involvement of the user, f o llowed by a three-year
engineering and manufacturing development (EMD) phase, which leads
to a normal production decision in the year 2000. This normal
progression of the program, in turn, would lead to the ini-' tial
site capability in around the year 20 0 2, or 2003, and a fully
operationally capable system, including both Brilliant Eyes and
Brilliant Pebbles by the year 2006. That is the baseline plan.
These schedules were included in my testimony to Congress, and they
are explicitly provided in the 180-d a y Report to Congress as
well. The reason I'm making a point of these dates is that the CBO
has misrepresented our planned schedule, as I will describe to you
in a moment. Now, under a normal program, the first site initial
operational capability, or IOC, w ould be around the year 2002.
However, in order to be responsive to the Missile Defense Act by
provid- ing an early fielding option for an initial site, we have
pursued a plan to field prototype hardware developed in the
demonstration and validation phase of the program as early as late
1997. This date, which coincides roughly with the end of the
demonstration and validation phase, is as early as we believe is
possible in conjunction with our event-driven strategy. I want to
emphasize that this fielding ac t ivity does not result from
production in any normal meaning of the term. We would field
prototypical hardware, trying to plan from the outset of the
acquisition program to do what we did with JSTARS in the Gulf War.
If our program is fully funded, such an initial site capability
could be achieved as early as 1997-as Deputy Secretary Atwood
testified-but 1998 would be a more likely date for achieving such a
contingency capability. In any case, there would be no dollar
implications associated with making suc h a decision be- fore 1995.
The program in 1993 and 1994, under the normal demonstration and
validation .. program, is the same whether this option is exercised
or not. If the option is exercised, there, Will be a dollar impact
in the 1995 time frame to be g in the necessary activities to field
the prototypi- cal hardware and have a contingency defense
capability by the end of 1997. This idea of fielding early
prototypical hardware is a new acquisition approach that we have
in- jected through the SDI program. Most notably, I consider our
successful advocacy for THAAD, orTheater High-Altitude Area
Defense, to be a major victory in our battles to overcome business-
2
as-usual attitudes. After some considerable debate in the
acquisition community, the Pentago n powers-that-be agreed to buy
on to this idea. and the THAAD contract -was let, as you probably
know, last Friday. The Lockheed team that won the THAAD contract is
now working on a pro- grain that will give us an early fielding
option in the 1996 time pe r iod using prototypical hardware. My
point here is that our efforts with THAAD represent real progress
in the way SDI pro- grains are being done in a fully coordinated
way in the Pentagon. When the truth is all out on THAAD sometime in
the future, you'll f i nd just about everybody got into the act
before that con- tract was awarded. So SDI is not a loose cannon in
the Pentagon. We are, in fact, executing a coordinated acquisition
program. I might say that the THAAD contract award was the
culmination of a 24- m onth effort. Some of you may recall the
early days when I started talking about THAAD and the idea of using
pro- totypical hardware as a part of our acquisition strategy.
While I never met resistance in this audience, I can tell you I met
considerable res i stance in the Pentagon. So THAAD is a major vic-
tory, in my judgment. My main point though is, as I said earlier,
that the key Pentagon officials agreed on our plan to implement the
Missile Defense Act. Secretary Cheney's July 2 cover letter to the
Congr e ss indi- cated that he had given instructions to the
Pentagon to execute the plan as a top national priority. So in the
Missile Defense Act, the Congress in effect said, "This is what we
want you to do; these are the priorities we want you to take," and
t h e Department's plan was fully responsive to execute the
prograrn that Congress had laid out. And, as I said earlier, to
satisfy the acquisition process of the Pentagon, our plan calls for
an event-driven program. If Congress cuts out events, or we fail ev
ents, or we delay events, because of budget cuts or whatever, then
the whole program slips-and I'll come back to the importance of
that point in a moment.
Progress with the Russians I think we can also point to a great
deal of progress in our discussion wi th Russia and the other
republics of the former Soviet Union, and with our allies. This
progress has been steady over the last eighteen months. I consider
that there was a real watershed when President Yeltsin, at the end
of January, spoke at the U.N., ca l ling for cooperation on a joint
global defense system-and it was absolutely clear to me that he was
talking about the kinds of things that we wanted to do. He said he
wanted to redirect the SDI program to take advantage of Russian
technology-and we are sy m pathetic to his proposal. Since then, I
think we have made a great deal of progress in moving in the
direction advocated by President Yeltsin-which was entirely
consistent with President Bush's redirection of the SDI program a
year earlier. In June, at th e Washington Summit, President Bush
and President Yeltsin gave impetus to the discussions by agreeing
to establish a very high level group to agree on how to create such
a Global Protection System. Dennis Ross, now Assistant to the
President for Policy Pla n ning, is leading the group on our side,
and Deputy Foreign Minister Georgi Mamedov is leading on the
Russian side. There was a High Level Group meeting in Moscow in
July at which time three working groups were established: one to
thrash out the specifics o f what is meant by the concept of a
Global Protection System, one to deal with the area of technology
cooperation, and one to deal with the agreed problem area involving
the proliferation of missile technology and weapons of mass
destruction. The High Lev el Group will also deal with any now
agreements or changes to existing agreements as necessary to bring
a Global Protection System into existence. We are an-
3
ticipating a follow-up meeting here in Washington very shortly,
and I am counting on there be ing progress at this coming meeting.
I can't help but note a meeting I attended in Erice, Sicily, a
couple of weeks ago when Acade- mician Yevgeni Velikhov came in
wearing an SDI tie. Now Dr. Velikhov is Chairman of the Russian
Academy of Science, as he w a s of the Soviet Academy of Science.
In the early days of SDI, he co-authored papers with a number of
people that were very, very negative on what were vying to do. That
was their Party line in a different era, an era of confrontation;
whereas today we are seeking to reflect an underlying principle of
cooperation. Accordingly, he has changed his position considerably.
He is a member of the Mamedov group, I might add. At the Erice
meeting, Velikhov said that -/,?e should replace Mutual Assured
Destruction wi t h Mutual Assured Protection as the underlying
principle upon which we design our national secu- rity interest. It
was clear from his discussion that he was thinking in terms of
cooperation on a Global Protection System under a new arms control
regime whic h would be multi-national in its basic framework-such a
defense system could provide protection on a global basis for the
en- tire world community, and we might operate it more as partners
than as adversaries in some kind of an arrangement involving a join
t command center, perhaps patterned after the model used in NATO or
in NORAD where our Canadian friends participate directly with us in
various com- mand and control activities. It was made clear that he
was thinking in terms of space elements in the Globa l Protection
Sys- tem-both sensors and interceptors, and that this Global
Protection System would be accomplished in consultation with our
allies, as I said earlier, in a multi-national framework. This
development was very hopeful. This Erice conference wa s an
informal meeting in an in- formal setting, of course. When Deputy
Foreign Minister Mamedov comes to Washington, I'm not sure exactly
what he will have to say. But, that will be when Russian statements
will really count because the High Level Group is t 116,3offinial
government to government forum for such discussions; and I look
forward to the outcome of those sessions with hopeful anticipation.
I think that it is somewhat sad that Congress is threatening to
pull the rug out from under us at just the ti m e when the
negotiations show the most promise that they have shown in nine
years for moving toward a negotiated outcome and a settlement to
many very contentious issues that have to do with the political
perceptions surrounding the ABM Treaty and other re l ated matters.
And I know something about the hard times in the past
negotiations-I spent five years in Ge- neva, and before then I was
worked these issues at the Arms Control and Disarmament Agency, in
backstopping all of our negotiations with the former S oviet Union.
I can say with authority that we have the first real opportunity of
ending up with agreements on how we will proceed to- gether to
build and to operate a Global Protection System. This does not mean
we're going to give away the family jewels; that's not going to
happen- and need not happen in order to work cooperatively to
mutually benefit from a Global Protection System. I believe that,
toward this end, we could agree on doing joint experiments, joint
simula- tions to understand and work thro ugh solutions for the
conceptual issues, modifications to the ABM Treaty regime that will
be satisfactory to both sides-and I think such an agreement may be
relatively close at hand.
Why the Congressional Backsliding? So I have to ask myself, in
coming back to the original point of my talk, "Why is Congress now
attacking our program? Why are they backing away from the Missile
Defense Act at this juncture?"
4
I think there are two sources of the reason why. There may be an
ideological reason that under- lies the entire pr9blem for some in
Congress-but there are two logical reasons whose merits can be
debated.
A Reduced Sense of Urgency First, there is a reduced sense of
urgency this year, that's clear. We are no longer on the heels of
the Gulf War. And Bo b Gates, the Director of Central Intelligence,
in his testimony indicated that it was unlikely that there would be
any new threat to the Continental United States within ten years.
He said it two ways: within this decade and within ten years. But
if you t a ke ten years, 2002 becomes a magic target-and that is a
piece of the litany in the current congressional de- bate. From my
own personal perspective, I don't believe the analyses that
underpin Director Gates' testimony take into account what the
situation w ould be like if the proliferation issues become
different over the next ten years than they were in the past ten
years. And I refer not only to the proliferation of technology, but
also of the technical know-how as citizens of the former Soviet
Union deal with their rather severe economic pressures and where
they have such a highly mar- ketable skill. I don't mean to throw
rocks at our new friendly colleagues and potential collaborators in
a Global Protection System in bringing this up. In fact, it is a pr
o blem that they willingly acknowl- edge and are concerned about
themselves. So I think that many in the Congress have developed a
false sense of security-perhaps like the sense of security that
many had before the Gulf War based on the rather commonly held
judg- ment that Saddarn Hussein could not develop nuclear weapons
any time soon. And we found out how wrong we were. Speaking
personally, I am very uncomfortable with taking a relaxed attitude
in this regard when considering the proliferation problem. But I
would point out, as I said earlier, that the year 2002, or 2003, is
a sound estimate for the IOC for the first site under the
President's baseline plan anyway, assuming that we don't exer- cise
the option to deploy prototypical hardware. Budget cuts wil l delay
this IOC for the baseline program. I pointed out earlier that there
are no budget requirements for at least two years to provide early
fielding options, so there is no FY1993 budget impact if this
option is decided upon now- either way. Our strateg y fundamentally
defers that decision to a time, at least two years hence, when we
can see how the threat develops, and how the testing progresses.
Budget cuts now delay all options, including especially these early
fielding options.
Flawed CBO AnalysIs Now I want to come to the second cause for
congressional backsliding: the CBO Report. I think the August 7
report, which draws from an earlier May report, is the root cause
of many of our problems. The CBO alleges that with $3.3 billio n in
FY 1993 (that is, a cut of $2.1 billion from the President's
request) and cutting our out-year budget in half (and I think it is
important that you understand that is part of their proposal),. we
can still deploy the initial site in the year 2002-the same as is
planned under the Administration's plan. And not only do they
allege that we can deploy at the same time frame as under the
Administration's plan for half the funding, but that we can do so
with less risk and less concurrency.
5
It is incredib le to me that such a naive and misleading
masquerade for serious analysis could be given the weight that this
report is being given. And I'm more than a little suspicious that
it was published on the 7th of August just in time for its use in
the floor deb a te on that date as the Bumpers-Sasser Amendment was
tabled. Attached is a copy of a letter I sent to Senator Warner and
Senator Nunn at Senator Warner's request evaluating the flawed
analysis in the August 7 CBO Report. But let me go through here, in
perh a ps more detail even in some cases than is in that letter,
some of my problems with that badly flawed analysis. Fundamentally,
if you believe you can cut over $2 billion. from our FY 1993 budget
and cut a half, some $20 billion, out of the FY 1993 through 1 997
five-year budget and deliver on the same schedule, and with less
concurrency and less risk than the Administration's program, then
after the meeting I want to talk to you over on the side; I have
this bridge and I would like to so- licit your investme n t in
purchasing it as a group venture. The CBO Report falsely represents
the Administration program. It claims, for example, that the budget
called for in the out years would lead to deployment of thefull
GPALS program in the year 2000. And, as I told you earlier, we
anticipate that year would be 2006 with the Admin- istration plan
and budget. That was presented in my congressional testimony which
the CBO had before they wrote their report-I checked it this
morning. They have no excuse for this misrepre- s e ntation. They
cannot justify this gross error by saying they didn't know because
our Report to Congress was not published until early July. So they
falsely claimed we planned a fully deployed system by the year
2000-that way, you see, they could allege to stretch the program to
"after 2005" while cutting our budget. They also pursued a
contorted analysis implying that we planned to deploy the initial
site in 1997 based on an earlier "production" decision, whereas, as
I described it earlier, we planned op- t ions to fabricate and
field prototypical hardware that could be exercised if the threat
develops, and if our testing shows it's warranted. As discussed in
our 180-Day Report to Congress, we could field prototypical
hardware in 1997, 1998, or 1999 under th e President's budget
depending on decisions to be made at least two years hence. But,
such decisions to field prototypical hard- ware for a contingency
capability would not involve a production decision or process. We
would make a production decision in th e year 2000 in any case, and
could have an IOC in the year 2002, or 2003, if none of those
options was exercised. I emphasize that we clearly stated our plan
to make a production decision in the year 2000-that was in our
Report to Congress. But they mis-ch a racterized our plan. They
called the Administration's possible decision to ex- ercise the
earliest of these options to fabricate prototypical hardware a
"production decision" and used that in a very trumped up definition
to achieve a high concurrency esti m ate. They totally ig- nored
the fact that in our report we explicitly stated that the
production decision would be made in the year 2000. Of course, if
they had accepted the Administration's clearly defined production
decision, then their definition of co n currency would lead to zero
concurrency in the Administration's program-and they apparently
sought to characterize the Administration's plan as involving a lot
of concurrency so they could justify stretching the program and to
allege to be reducing concur r ency. This is particularly
intriguing when you learn from their fine print in a footnote that
they de- fined as "production" a decision at Nfilestone H to build
low-rate initial production, or LRIP, equipment for testing in
full-scale development or engin e ering and manufacturing
development. This is most curious, because we are directed by law
and Administration directives to use LRIP equipment in Initial
Operational Test and Evaluation (IOT&E) prior to making a
production de- cision. And IOT&E normally oc curs during the
engineering and manufacturing development
6
phase after Mlestone H. With their definition, one always gets
100 percent concurrency for a nor- mal acquisition program. Our
innovation of including a Phase I of IOME in our demonstration an d
validation program, meant that they only could come up with 64
percent concurrency for us even with this trumped up analysis. So
they resorted to backing up further into the Dem/Val phase of the
program, referring to the possible fabrication of prototyp e s as a
production decision to suggest an even higher level of concurrency.
Now this is more than a little curious way to define concurrency.
But it goes beyond that. They are basically dishonest in claiming
that their definition for production is the DoD d efinition. And it
is absolutely outrageous to characterize the fabrication of
prototypical hardware as a produc- tion decision when it was made
explicitly clear in our Report to Congress that the production
decision is the year 2000, and that we could dec i de earlier to
fabricate:prototypes if we think we need them on the basis of
demonstrated capability and the developing threat. Of course, if
they had admitted that our production decision was in the year
2000, their false suggestion that our full system w o uld be
deployed in the year 2000 would have been apparent. Now they went
further with more nonsense to justify their arbitrary budget cuts.
For example, they falsely rationalized the deep cuts in such
activities as system engineering and integration, test and
evaluation, and risk mitigation by alleging that such critical
activities are unessential, or as they said, and I quote . .....
relate only indirectly to the system to be deployed." Give me a
break! This really is utter nonsense. Since when does anyon e build
a system without system engineering and integration? And since when
does one cut out the funds for the risk mitigation and create a
less risky program? Finally, I should let David Chu speak for
himself, but I think to suggest, as the CBO does, that their $3.3
billion plan would support his preferred option is grossly
unprofessional. I'd love to have David and his staff subject the
CBO plan to the same scrutiny that they gave SDIO's plan. I can
guarantee you it would not survive one day's serious loo k in the
Pentagon. This all leads me to make a half-serious suggestion that
some of our friends in Congress ask for a GAO review of the CBO's
Report. They should have some fun with that, especially if such a
review were done honestly. The only good thing I can say about this
CBO report is that it included some fine print dis- claiming
responsibility for what I think is a pretty foul portion of magic
elixir befitting the snake oil salesmen of another era. It
basically says, "Let the buyer beware." So if you r ead the report,
look long and hard, you'll eventually find disclaimers about their
schedules; that their plan might, in fact, not cost less, but more,
after all is said and done; that concurrency may not be all that
important anyway; and so on. The fact i s that the CBO option
touted by the Bumpers-Sasser Amendment and masqueraded as Dr. Chu's
low concurrency option is fundamentally a product of unprofessional
analysis. It is not Chu's option. In fact, it is no seriou's
acquisition program at all. It is a g uaranteed recipe for
failure-and would provide no effective defense for the American
people.
There Is a Viable Plan, But Will Congress Support It? The
President's request of $5.4 billion supports a low-concurrency,
moderate risk program- and we judged mode rate risk because we are
dealing with a complex system of systems-not be- cause the program
for any of the system elements themselves, taken singly, is risky.
Otherwise it would be a low risk program on an item-by-item
basis.
7
The President's plan is t o reach an IOC, if conducted in the
normal way, in the year 2002 or 2003. It provides options for
fielding prototypical hardware earlier, as early as 1997 and more
likely in 1998, but decisions to exercise these options are to be
made at least 2 years hen c e. Our acquisition strategy is event
driven. And I'll repeat again, if Congress cuts our budget, they
will delay key events, and that will delay the schedule-and
probably increase overall costs. The $1.1 billion cut, as suggested
by the Senate Armed Servi c es Committee or by the House Armed
Services Committee, would end up causing delays in the dates I've
just given you. Cer- tainly, it would cause a year's delay in our
ability to exercise a prototypical hardware option, and the 2002
date would also be at r i sk. The $2.1 billion cut called for by
the Bumpers-Sasser Amendment would leave no viable ac- quisition
program beyond Theater Nfissile Defense. Senator Nunn, during the
August 7 floor debate, referred to the $3.3 billion plan and said,
that this budget " w ould stretch out the program to such a degree
it would render implausible any claim by the Congress that we are
on a steady course toward deployment .... .. I can only say "Hear,
hear!" Indeed, the $3.3 billion would sup- port only Theater
Defense and R&D we could have defense for allies but not for
Americans.
Closure Finally, let me just say that in 1988 George Bush,
campaigning for the Presidency at that time, stated that the
technology is here to support strategic defenses; the issue is
political will to take things out of the laboratory and to move
them to deployment. He promised that he would pick the architecture
in his first term, and that he ultimately would not leave America
defenseless. I would submit that he has fulfilled his part of the
bargai n . The GPALS, or Global Protection Against Limited Strikes,
idea, which is his architecture, folds directly into the Global
Protection System subsequently proposed by President Yeltsin and
now being advocated by our new friends in Russia as well as ourselv
e s. The Nfissile Defense Act of 1991 adopts all of the key ele-
ments of the President's program with a shift in priorities, which
was acceptable to the President last year-that is, to move ahead
with deploying the ground-based defense so long as there is r o-
bust funding for developing space-based interceptors.
Unfortunately, Congress is now apparently playing around with
welshing on this aspect of the deal this year. In the final
analysis, Congress now holds the fate of the program in its hands.
They prov ide the funds-that's the way our system works. I have no
reason to suggest changing our system, and I only hope that for the
good of all Americans that Congress does the right thing this time
around.
4
8
DEPARTMENT OF DEFENSE STRATEGIC DEFENSE INITIATIVE ORGANIZATION
WASHINGTON, DC 20301-7100
A ugust 10, 1992
Honorable John Warner Ranking Minority Member Committee on Armed
Services United States Senate Washington, DC 20510
Dear Senator Warner: Thank you for the opportunity to comment on
the August 7 CBO report regarding issues of concurrency and cost
estimates for the SDI program--particularly those est'imates that
allege to support a 2003 deployment of an initial ground-ba sed
interceptor site. Let me discuss these two issues in turn.
Concurrengy_. I must say that I am surprised by the lack of
understanding in the CB01s discussion on concurrency and
characterization of our program as presented in our June 1992
Report to Con gress on our Plan for DeRloyment of Theater and
National;Ballistic Missile .Defenses. For example, the CBO report
states that its definition of concurrency depends on the date at
which production begins-- and then alleges that this date is not
clearly def i ned by the Administration's plan. Yet our reRort
clearly states that production @egins at Milestone III (as in
every-standard acquisi- tion Rrogram). which occurs in our Rlan in
the year 2000--as shown on Figures 5 and 7 and as explicitly stated
on page 2 3 . Here, in discussing our acquisition strategy as
illustrated by Figure 5, the report indicates that the
Administration plan employs "a normal acquisition strategy
involving a robust five- year Dem/Val program with heavy user
involvement, followed by a th r ee year EMD phase and concluding
with a production decision in the year 2000 for items produced in
quantity.,, Thus ifi our baseline program, a production decision
for the 11100011 interceptor missiles of the CBO report would be
made after completion of I OT&E Phase I and Phase 2, as shown
in Figure 7 of our 180-day Report to Congress. The Administration's
baseline Rlan is, therefore, a "low concurrency" Rrogram by the
CB01s own definition.
2
is hard to imagine how the CBO could misunderstand our acquisi
tion strategy--or Kh_y they would choose to characterize our Rlan
solely in terms of an option to field contingenc cARability in 1997
using Dem/Val hardware as a 1997 Rroduction decision. which it
certainly is not. In fact, our plan considered three conti n gency
fielding options, none of which involve production hardware--they
all involve 60 Dem/Val interceptor missiles, with fabrication of
those Dem/Val missiles beginning-at some future time fas early as
1996)., pending evaluation of progress in our baseli n e program
and our perception then of the evolving threat. "Concurrency" for
the 60 Dem/Val missiles would vary depending on which of the three
options, if any, is selected in conjunction with IOT&E Phase 1:
option 1 (High Concurrency) leading to an initia l contingency
capability as early as 1997 would initiate fabrication of the
initial 12 Dem/Val missiles after 2 tests; the next 24 Dem/Val
missiles after 6 tests; and the final 24 Dem/Val missiles after 8
tests. Option 2 (Moderate Concurrency) leading to a n initial
contingency capability as early as 1998 would initiate fabrication
of the initial 12 Dem/Val missiles after 6 @.ests7. the next .2.4
Dem/:Val missiles after. 8 tests-@. and. the final 24 Dem/Val
missiles after all ifte'sts. Option 3 (Low Concurre ncy) leading to
an initial contingency capability as early as 1999 would initiate
fabrication of the initial 12 Dem/Val missiles after 8 tests; and
the remaining 48 Dem/Val missiles after all 11 tests.
In this analysis, I have used the CBO estimate of 11 I OT&E
Phase 1 tests. We may actually conduct more (or less) testing, but
the basic point will be the same. Meeting the dates above depends
on funding and technical progress, but our overall strategy is
"event driven", and the conclusions regarding concurre n cy would
not be affected by schedule slips. I would also observe that, if
one of the above options is exercised, the 60 Dem/Val interceptor
missiles composing an interim contingency capability will be
replaced later by normal production missiles, produced after
Milestone III, which is planned-for the year 2000. In any case, it
should also be kept in mind that the Committee Bill Rending action
on the floor makes no decision to groceed with any of the above
options to field an early initial contingency-dapab i lity. In
fact, no such decision is called for even under the
Administration's Rlan for several years. The central issue of
concern is the Administrationfs and the Committee's baseline plan
leading to a production decision in the year 2000. That baseline R
roaram involves low:concurrency by the CBO's own definition.
3
I would note, with some humor, that in their discussion on
concurrency, which builds upon a premise that low concurrency is
better, the CBO notes that in a 1988 study, they found "no strong
relationshiR between concurrency and the two measures associated
with the success or failure of weapon programs: cost and schedule
delay". This obscure comment suggests that too,much is being made
of the risks associated with concurr&ncy. The-more importa n t
variable, I would suggest has to do with the robustness of the
baseline development Rrogram. including sound risk mitigation
efforts. It is therefore ironic that the CBO report couples its
allegations of high concurrency in our Dem/Val program, which is ,
by any reasonable measure, a robust testing effort to mitigate
risk, with suggestions that cutting severely the support for those
very risk mitigation activities would achieve lower concurrency and
lower risk in our baseline program aimed at an initial o perational
capability in 2002-3. This is an absurd DrOROsition on its face.
Costs. In fact, the CBO cost estimates, which adopt the analysis
in their May 1992 report.on Costs of-ALternative-ARPXoaches to
SDI.. are simply fallacious. In the fikst place'tha t report states
that the CBO reflects the Administration's current estimates of
cost--but I simRly cannot reconcile the gross discreRancies between
our cost estimates. as presented in our.june 1992 180-day ReRort to
Congress, and the CBO estimates. For ex a mple, there is a
difference of almost $900 million in FY1993 for the Limited Defense
System line item alone--not to mentiondiscreRancies of over $400
million for work in the Other Follow-on and Research and SuRRort
line items that suRRort the Limited Defe n se Syst and Theater
Missile Defense line items--as I discussed in my hearings before
the SASC and as discussed in our June 180-day Report to Congress.
Secondly, the CBO report is factually very wrong in stating that
$3.3 billion in FY1993 would support "D r . Chu's preferred
approach". Dr. Chu supRorts the baseline event-driven strategy
described in the June 1992 DoD 180-day ReRort to Congress, which
leads to a Milestone III decision in FY2000 and an initial
capability with production interceptors in the 200 2 -2003 time
frame--provided the technical progress stays on schedule. Less
near-term funding than in the DoD plan will slow progress, delay
the key events and stretch the schedule beyond-that alleged to be
achievable with the CBO's Alternative III. Thus, t h e CBO makes a
gross understatement in qualifying that the CBO cost estimates for
"Alternative III" (which CBO characterizes as Dr. Chu's option)
makes assumptions "not discussed in Dr. Chu's memo". I would like
to have Dr. Chu and his staff subject the CB O's Alternative III to
the same scrutiny applied to the SDIO plans before he concurred-in
them, as
4
reflected by our June Report to Congress. There is no chaDgg that
the CBO option would survive any serious scrutiny by the DoD
acquisition community. Th e fact is that Alternative III of the
May-1992 CBO report has nothing to do with the baseline Rrogram
presented in the Secretary's 180-day Report to Congress to V hich
Dr. Chu Lqpd every other senior DoD official with
acauisition-resRonsibil- ities) concu r red and which called for
$5.4-billion in FY1993. In fact, the $1.1 billion cut by the SASC
jeopardizes the schedule for meeting a 2002 initial operating
capability--regardless of whether an early contingency capability
using Dem/Val hardware is sought in the future. An additional S1
billion cut would be devastating--leaving no viable SDI
develop_ment program beyond Theater Missile Defenses.
I would note that on page 36 of our June Report to Congress, this
baseline pr Judged by the QoQ acguisition community to be "moderate
risk", primarily because of the complexity of integrating a system
of systems. The CBO suggested cuts would clearly turn i t into a
high risk Program. In my judgement, it would destroy our ability to
mitigate risk in meeting any pre- assigned schedule. In short. the
CBO Alternative III. which the CBO most recently masguerades as Dr.
Chul's "low concurrency" program. is naive and grossly misleading,
It is not Dr. Chul-s agggisition program: it is not a serious
acquisition Rrogram at all. It is -a gMaranteed recipe for failure.
To sugRort it is to suRRort no active defense for the American
peoRle.
I have also enclosed a copy of my response,to Senator Levin's
question for the record following my April 9 hearing regarding the
May 1992 CBO report.
HENRY F. COOPER Director
A ttachment: As Stated
cc: Honorable Sam Nunn
}}